DEWA Water Distribution Networks

Year: 2020   |   Location: Dubai

Supply, installation, testing and commission of Siemens Flow Meters for Water Distribution Networks in Dubai & Hatta

Scientechnic - Industrial Stock Sales (ISS) was awarded the scope for the supply, installation, testing and commissioning of DN 300 Siemens Electromagnetic Flow Meters for DEWA, through M/s Green Oasis General Contracting Co. LLC. ISS was awarded this project, based on its previous successful installations and demonstration of the IP68 feature of the Siemens MAG Flow Transmitter, as per DEWA requisites.

The project constitutes the use of the remote version of Siemens SITRANS FM MAG 8000 CT Electromagnetic Water Flow Meter, which is best suited for 

portable water and/or treated water applications, with an ingress protection for both the sensor and the transmitter at IP68. The flow meter is suitable for Zero D installations on both the upstream and downstream pipelines and comes with 230V AC or 24V DC power options. It also has an option for external or internal battery usage.

As part of the schedule, the Site Acceptance Test (SAT) for the MAG 8000 CT was successfully conducted and completed by the Industrial Stock Sales team, in the presence of all the project stakeholders.

  • Scientechnic - Industrial Stock Sales (ISS) was awarded the scope for the supply, installation, testing and commissioning of DN 300 Siemens Electromagnetic Flow Meters for DEWA, through M/s Green Oasis General Contracting Co. LLC. 
  • Project constitutes use of the remote version of Siemens SITRANS FM MAG 8000 CT Electromagnetic Water Flow Meter, best suited for portable water and/or treated water applications, with an ingress protection for both sensor and transmitter at IP68.  
  • Flow meter is suitable for Zero D installations on both the upstream and downstream pipelines, comes with 230V AC or 24V DC power options and has an option for external or internal battery usage.
  • Site Acceptance Test (SAT) for MAG 8000 CT was successfully conducted and completed by ISS in the presence of all the project stakeholders.

Gallery

See Also

@Scientechnic

For better web experience, please use the website in portrait mode.